Adani Energy Solutions Limited (AESL) has been awarded a crucial 2,400 MW power transmission project in Bihar, designed to evacuate electricity from the upcoming Pirpainti thermal power plant. The contract, secured through the Tariff-Based Competitive Bidding (TBCB) route, is projected to generate approximately Rs 500 crore in annual tariff revenue once operational.
The project, officially titled 'Evacuation of Power from 3X800 MW STPP Pirpainti', will be executed under a special purpose vehicle (SPV) named Vikramshila Power Transmission Ltd. Completion is targeted for the fourth quarter of 2028, significantly bolstering Bihar's energy infrastructure.
Strengthening Bihar's Grid and Energy Security
Beyond facilitating power evacuation from the new thermal station, this extensive transmission network is expected to enhance Bihar's overall electricity infrastructure, improve grid reliability, and ensure a more dependable power supply for the state's growing demands. Kandarp Patel, CEO of Adani Energy Solutions, emphasized that the project will establish a robust transmission system while reinforcing Bihar's power backbone, ultimately improving grid resilience and supporting India's long-term energy security.
Project Scope and Financial Impact
Upon completion, the project will add 881 circuit kilometers (ckm) of transmission lines and 3,160 MVA of transformation capacity to AESL's existing portfolio. This expansion will bring the company's total transmission network to 30,683 ckm and its transformation capacity to 146,585 MVA. With this latest win, AESL's transmission capital expenditure pipeline has increased to approximately Rs 91,500 crore.
Key Infrastructure Details
- Substations: Construction of four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli, and Begusarai, along with associated transformation infrastructure.
- High-Voltage Corridors: Development of 400 kV double-circuit (DCDS) lines connecting Pirpainti-Jhanjharpur, Pirpainti-Begusarai, and Begusarai-Bakhtiyarpur.
- Additional Lines: Inclusion of 220 kV DCDS transmission lines between Jhanjharpur-Bethauli and Begusarai-Begusarai Town.
- Ancillary Works: Line-in-line-out (LILO) arrangements for existing 220 kV and 132 kV transmission lines at Jhanjharpur, and construction of 400 kV line bays at Bakhtiyarpur Grid Substation (GSS).
Despite the significant project win, shares of Adani Energy Solutions were observed trading on a flat note, settling at Rs 1475 in the current session against a previous close of Rs 1478. The firm's market capitalization stood at approximately Rs 1.80 lakh crore.